Test Specification TC23.1
Test Specification Definition
ID | TC23.1 |
---|---|
Reference to Test Case | TC23 |
Title of Test | Verification of the reliability of Substation Automation Systems (SASs) with redundancy in the communication network |
Test Rationale | With the use of IEC 61850 standard, substations are nowadays becoming digitized and automated with digital relays/IEDs and a LAN based communication network for connecting these IEDs. Failure of the communication, even for the few milliseconds, may jeopardize critical functions such as protection and lead to catastrophic effects within or beyond the substation impacting the operation of grid. New redundant architectures, notably parallel redundancy protocol (PRP) and high High-Availability Seamless Redundancy (HSR) from IEC 62439-3, have been used to increase the reliability of IEC 61850 LAN based substation automation communication networks [1]. PRP provides high reliability through two independent LAN networks. The PRP enabled nodes are connected to these two isolated networks, which operate in parallel as shown below in Fig. 1 below. Frames are duplicated in the source and are sent over both networks; the destination PRP enabled node receives packets from the first network and accepts it, if it is correct, and then the copy from the second network will be discarded as duplicate. HSR operation is similar to PRP but HSR uses a single LAN with a ring topology and it uses two independent paths (clockwise and counterclockwise). Both architectures aim to provide an ideal “zero recovery time” with no packet loss. This test aims to investigate the reliability of these two recent redundant communication networks in substation automation. [1] International Electrotechnical Commission IEC 62439-3:2016 Industrial communication networks - High availability automation networks - Part 3: Parallel Redundancy Protocol (PRP) and High-availability Seamless Redundancy (HSR) [2] S. Kumar, N. Das and S. Islam, "High performance communication redundancy in a digital substation based on IEC 62439-3 with a station bus configuration," 2015 Australasian Universities Power Engineering Conference (AUPEC), 2015, pp. 1-5, doi: 10.1109/AUPEC.2015.7324838. |
Specific Test System (graphical) | The specific test system consists of a real-time grid simulator, protection IEDS, Ethernet switches (x2), communication cables (x2). The real-time simulator is used to model the power system dynamics as well as some IED functions such as Merging unit (generating sampled values), circuit breaker functionality. The physical IEDs (for protection) will be connected to the real-time simulator through the two redundant communication networks in a C-HIL setup. Fig. 1: PRP Network Topology Fig. 2: HSR Network Topology |
Target measures |
|
Input and output parameters | Input parameters:
Output parameters:
|
Test Design | The test design is as follows.
|
Initial system state | Normal system state where there is no failure in the power and communication system. There will be a normal GOOSE (status update) between IEDs (also between IED and breakers), and SV streams from OPAL virtual MUs to the physical IEDs. |
Evolution of system state and test signals |
|
Other parameters |
|
Temporal resolution | 100 us |
Source of uncertainty | Background traffic data rate, configuration of the communication network (ethernet switches), Network devices or IED's capability to support the PRP/HSR architectures. |
Suspension criteria / Stopping criteria | Exceeding of quality attributes:
|