Experiment Specification 02.01.01
Hardware-in-the-Loop for inverter controller validation in real conditions
ID | 02.01 |
---|---|
Reference to Test Case | 02 |
Title of Test | Complying with the fault-ride-through (FRT) requirements while maintaining power sharing |
Test Rationale | N/A |
Specific Test System (graphical) | |
Target measures | Inverter power injection, load voltage and frequency, inverter currents |
Input and output parameters | Input:
Output:
|
Test Design |
|
Initial system state |
|
Evolution of system state and test signals | The system goes from normal operation (operation close to nominal voltage and frequency) to operation under grid faults, to test the inverter control algorithms |
Other parameters | N/A |
Temporal resolution | N/A |
Source of uncertainty | Impedance of load and lines, inverter sensors operation |
Suspension criteria / Stopping criteria | Abnormal current/ power injections from inverters |