Aim is to evaluate system services and connected activation patterns of an aggregator platform during and/or after a functional disruption in the near location (e.g., Fault Ride Through, blackstart assistance, virtual inertia provision)
The test scenarios serve the validation of continuous service provision under various disruptions and system settings.
Control signal before and after the disruption as an input. Active power as an output.
30 minute long simulation period during which a disruption is introduced that breaks the connection of communication and/or electricity from aggregator/public grid.
Initially the system service is operating normally and the grid is functioning without disruptions.
A disruption is introduced. Communication and/or grid connection is momentarily lost. System(s) providing the flexibility service is then evaluated to see if nornal operation can be established again.
communication latency, communication signal, voltage and current observed from the DER(s)
1 second resolution
Only certain amount of different kind of disruptions can be tested for. In other words, everything cannot be tested.
30 minutes or permanent loss of communication and/or grid connection