Once the BS generator is started by the BS controller to reenergize the grid, an interval follows within which several resources are reconnected. The main challenge that the BS generator and the system itself faces is the stability of frequency and voltage. Due to its nature, the requirements for this operating state should not be very strict. Nevertheless, rudimentary stability should always be maintained in order to avoid a new blackout. This test aims at evaluating the system’s capability to cope with the imbalances and maintain frequency as well as voltage stability within the required limits.
The above test system is based on the MV distribution network benchmark application example by CIGRE1
Input parameters
Output parameters
The test is carried out in a way that emulates the system behaviour after a black out. This implies the initial disconnection of lines and loads through the controllable circuit breakers and the start-up of the BS generator (BESS on Bus B-5). In this way, the system is sectionalized to its minimal connectivity state.
N/A
A sampling time of <100 ms is required for the accurate measurement of frequency and voltage variations.
Apart from the measurement uncertainties due to the instruments’ accuracy, additional uncertainties may be introduced by the communication channel delays between the controller and the DER units. In addition to that, the system operation is subject to uncertainties due to:
Environmental conditions
Consumers’ demand
Grid parameters variability, i.e., resistance and inductance
The test should be suspended and restarted if one of the quality attributes described in the TC is not met. If stability is not ensured during the various reconnection actions, the control parameters should be readjusted and the test repeated.