Experiment Specification TC12.TS02.ES01
Co-Simulation of Electric Boiler Activation for Excess Power Consumption with Model-predictive Control
Research Infrastructure
N/A
Experiment Realisation
The experiment is implemented as co-simulation using mosaik with a simulator synchronization step size of 15 minutes.
Experiment Setup
Dedicated simulation components are implemented as FMUs for Co-Simulation:
- power system simulation: the power system is implemented as pandapower model, using consecutive power flow calculations to simulate the power system; the electric boilers are represented as PQ loads;
- thermal network simulation: the local heating network and the electric boilers are modelled with Modelica (and compiled with Dymola); this model includes the proportional controllers that actuate the boilers;
- model-predictive controller: the controller logic is implemented in Python
Experimental Design and Justification
Precision of equipment and measurement uncertainty
N/A
Storage of experiment data
The output from the individual simulation components is stored as time series data (HDF5 data format).
Last modified 09.03.2022